Hi Yogesh
We had the same issue as you. Almost certainly, your planned orders are being subject to detailled scheduling after arrival in ECC. You need to configure a production scheduler with "no detailed scheduling" set in ECC for each plant. This should then be added to the material master data in field MARC-FEVOR. After this your planned orders will only display the basic dates and these will match those in APO.
Chris