Hello,
I'm trying to calculate percentage overhead (overhead as a % of total cost of production) using the usual overhead group, overhead key ,costing sheet, etc.
Also put the overhead group in the material master.
Although I am getting it correctly as part of product cost planning, when it comes to calculating this overhead on a production order, it does it based on 'total actual costs' posted to the order. I want it to calculate the % overhead based on the standard cost of actual production (the target cost).
I would really appreciate some help on this.